Dear Mr Lee,
Thank you for taking the time to meet with me from INFILLION today regarding your schedule goals. It’s been a pleasure talking to you and discussdiscussing our job schedule and also our difficultydifficulties.
We hope to receive your company's deposit 20%(RM 39,503.80) by next Tuesday(23Tuesday (23rd of April) so that we can deliver our curtaincurtains for unicityUnicity according to your timeline on timetimeline.
Schedule(Based on Deposit pay on Tuesday)
Level 6 to Level 10: all tracktracks and sheersheers to be complete before 30th30 May 19 (curtain(curtains will be hanging around 29 to 30 May).
Level 11 to Level 12: all curtaincurtains and sheersheers to be completedcomplete before 18th18 June 19.
Hopefully, we can start the work on next Tuesday or early next week.
Looking forward to hearing from you.
We extend our apologyapologies for the inconvenience.