Regarding Unit 10 PGB50BB011, in last week (Wednesday), SCT competed for the job and doid the pressure test for the tank. And nNext day, SCT charged up the pressure of N2 and water until 6.5 bar; after that, put back to system operation condition. And uUntil now, almost 5 days SCT monitored the system, we never fiound anything abnormal in the system pressure,. fFor your information, I will be attaching the PGB cooling water system pressure trend.

And now
, we request for Tank No 2 ( 10PGB50BB021) PTW. Please consider fhaving it work continualously to work , Bbecause SCT consider fors manpower charge and installation in the work schedule. And tThat installation schedule, the last time I already sumbmitted to PLP, but that time I never geot any comments from PLP. And SCT hopes PLP to releases the PTW. If you need any more detail or clarification, please arrange a meeting and I will explain to PLP.

The text above was approved for publishing by the original author.

Previous       Next

免费试用

请输入您的信息
请选择修正的语言

查看我们的 Google Docs校对扩展程序!

eAngel.me

eAngel.me is a human proofreading service that enables you to correct your texts by live professionals in minutes.